Contract/projects

Autostrada Completes Tunnel Section on Kyiv Metro Extension

Kyiv Metro extension

Autostrada has completed a tunnel section beneath European Union Avenue as part of the Vynohradar extension to Kyiv’s Syretsko-Pecherska Metro Line. Work has now moved on to the installation of engineering networks.

A micro-TBM is being used to install the stormwater drainage system and has completed 460m of the planned 750m drive. Electricity and communications cables are also being laid.

Meanwhile, Autostrada is progressing with the assembly of its Viktoriia tunnel boring machine (TBM). More than 70% of the Herrenknecht machine has been delivered to the site. Key components and systems already installed include the operator control console, gearboxes, belt conveyor, service platforms, power transformer, electrical cabinets, pumps, cutterhead drive motors, cooling system and hydraulic oil tank.

Designed to operate in the water-saturated ground conditions along the alignment, Viktoriia will excavate the running tunnel between Syrets and Mostytska stations.

Manufacturing of the precast concrete tunnel segments is also under way at Autostrada’s production facility. The company expects the TBM to achieve an average daily advance of 10–12m, installing eight to 10 lining rings per day, equivalent to 56–70 segments.

The 3.78km Vynohradar extension will extend the Syretsko-Pecherska Line from Syrets station and includes two new stations: Mostytska and Prospekt Pravdy.

The project combines cut-and-cover construction with underground tunnelling. One of its key engineering features is an approximately 1km-long, double-deck tunnel, with the tracks arranged on two levels. This configuration is intended to reduce disruption to existing urban infrastructure and accommodate construction within Kyiv’s densely developed urban environment.