Chennai Metro Rail Ltd (CMRL) has completed a 1.08km underground tunnel drive beneath a densely populated residential area in North Chennai, India. Tunnel boring machine (TBM) Kurinji reached the Srinivasa Nagar North Shaft on 13 November 2026, completing the drive in 351 days.
The machine began tunnelling from Kolathur station on 27 November 2025 and encountered challenging geological and alignment conditions along the route.
One of the main challenges was negotiating a sharp curve with a radius of just 230m through varying ground conditions, ranging from soil and weathered rock to hard rock. The TBM also passed beneath or close to more than 70 borewells and open wells in the densely built-up residential neighbourhood.
CMRL described the breakthrough as the first on Package C5UG06, highlighting the technical challenges involved in tunnelling beneath the heavily developed area.
Kurinji is one of four TBMs – alongside Mullai, Marutham and Neithal – deployed to construct the 5.8km underground section of Corridor 5 under Chennai Metro’s Phase II programme.
Corridor 5 extends for approximately 47km, of which 41.2km is elevated. The underground section includes five stations and two ramps. Tata Projects is executing the underground works, with funding support from the Japan International Cooperation Agency (JICA).
CMRL also reported that a cumulative 3.78km of tunnelling had been completed on the corridor.
The breakthrough was attended by CMRL managing director Ashish Chatterjee, director of projects T Archunan, and senior representatives from Tata Projects and the project’s general consultant team.
Chennai Metro Phase II is an approximately 119km expansion programme comprising three corridors, with more than 76km of elevated sections and around 43km of underground sections.