Michigan governor pauses permits for Enbridge’s Line 5 tunnel project

Line 5 tunnel project

Michigan Governor Gretchen Whitmer has directed state environmental regulators to suspend further action on permits for Enbridge Energy’s proposed Great Lakes Tunnel Project beneath the Straits of Mackinac, introducing further uncertainty over the infrastructure scheme.

The directive, announced on 24 November 2026, instructs the Michigan Department of Environment, Great Lakes, and Energy (EGLE) to pause action on the project’s resource permit and pending wastewater permit until outstanding legal questions are resolved.

The decision follows a Michigan Supreme Court ruling on 31 July 2026 concerning a separate approval issued by the Michigan Public Service Commission (MPSC) in 2023 for the same proposed tunnel.

The court found that the MPSC’s environmental review had not adequately considered certain environmental impacts. It vacated the commission’s approval and returned the application for reconsideration in accordance with the court’s ruling. The court subsequently denied Enbridge’s request for rehearing in September.

EGLE had issued its resource permit for the tunnel project on 15 July 2026. However, the Supreme Court’s subsequent decision prompted the state to review the implications for the environmental permits already issued. The wastewater-discharge permit remains pending.

Whitmer said the permitting pause reflected the need to resolve the legal questions arising from the court’s decision.

“Protecting the Great Lakes and the people who depend on them has been a top priority of mine since day one,” she said. “I have always said my ultimate goal is to get Line 5 out of the water. Just one spill threatens irreparable damage to our water, our economy, and our way of life.”

The governor added that Michigan would continue to prioritise the protection of its water resources, environment, public health and communities.

The proposed Great Lakes Tunnel would accommodate a replacement section of Enbridge’s Line 5 pipeline, which currently runs along the bed of the Straits of Mackinac, connecting Lake Michigan and Lake Huron. The existing crossing consists of two pipelines carrying crude oil and natural gas liquids.

The proposed utility tunnel is intended to house a replacement pipeline section beneath the lakebed, moving the infrastructure away from its current underwater location.

The project has faced sustained opposition from environmental organisations and Native American tribal communities, which have raised concerns about the potential consequences of a pipeline leak in the Great Lakes. Enbridge, meanwhile, maintains that Line 5 is important to regional energy supplies and has continued to pursue the tunnel project through the permitting process.

The latest directive adds another obstacle to the project’s development. Although EGLE’s permitting activity has been suspended, the announcement does not constitute formal cancellation of the tunnel project. Its future will depend partly on the resolution of the outstanding legal and regulatory issues.