The sixth and final tunnel boring machine (TBM) has been launched for Package CP101 of the Metro Manila Subway project in the Philippines. The launch marks the deployment of all six TBMs assigned to the project’s largest construction package.
CP101 is being delivered by a joint venture comprising Shimizu Corporation, Fujita Corporation, Takenaka Civil Engineering & Construction and EEI Corporation. The contract covers approximately 9.5km of twin-bore tunnels with an internal diameter of 6.1m, together with four underground stations: East Valenzuela, Quirino Highway, Tandang Sora and North Avenue.
The joint venture is also constructing a depot comprising 45 buildings, including maintenance and training facilities.
Six TBMs deployed for CP101
Four of the six TBMs have already completed their excavation drives. The fifth machine was launched on 7 September, while the sixth was recently launched from Tandang Sora. The latest machine is scheduled to reach Quirino Highway Station by the end of 2027.
Overall progress on CP101 has reached 62%. Station construction is also 62% complete, shield tunnelling is 71% complete and building construction stands at 27%.
The contract is valued at approximately JPY245bn (€1.39bn), making it the largest contract awarded for a single urban railway package financed through a Japanese yen loan. Completion is scheduled for the end of 2030.
Metro Manila Subway development
The Metro Manila Subway is one of the Philippines’ largest public infrastructure projects. Financed through a loan from the Japan International Cooperation Agency (JICA), the overall project has a reported cost exceeding JPY800bn (€4.52bn). Construction began in February 2019.
The planned 33km underground railway will connect Mindanao Avenue in northern Metro Manila with Ninoy Aquino International Airport to the south. The scheme includes 17 stations, a depot and associated facilities.
Early contractor involvement and construction improvements
Following the award of CP101 in February 2019, the Shimizu-led joint venture reviewed the original design under an Early Contractor Involvement arrangement.
Its recommendations included replacing the New Austrian Tunnelling Method (NATM) with shield tunnelling, simplifying station layouts and reducing the number of underground station levels. According to the joint venture, these changes shortened the original construction schedule by 10 months.
The joint venture has continued to review construction schedules, quality and safety as the project progresses. Measures include prioritising construction areas to facilitate land acquisition and early site access, revising construction plans in response to progress, and introducing interim specifications for systems such as tunnel ventilation.
Japanese specialists in rigging, formwork carpentry and plastering have also been deployed as instructors to support the implementation of Japanese-style quality and safety management practices.
Workforce and technology transfer
The joint venture is supported by a multinational team of approximately 1,300 people. It is increasing the number of staff sent to Japan for construction management training as part of its technology-transfer commitments, with the aim of developing local engineering capabilities.
Local employment is also a major part of the project. Approximately 7,000 Filipino workers are currently working on site.