Swedish water and waste management company VA SYD has withdrawn the contract notice for the wastewater tunnels and shafts forming part of its MAXIMA wastewater treatment system, following a reassessment of project risks.
The procurement notice was published in early June but has since been withdrawn after uncertainties emerged over access to land required for the construction of tunnel shafts.
According to MAXIMA programme director Christer Hallgren, the risk was identified during preparations for the environmental permit application and the process of securing utility easements. VA SYD concluded that proceeding with the existing procurement strategy would expose the project to excessive cost risks.
The company said that the processes for obtaining utility easements and environmental permits are continuing as planned. Work is also under way to clarify the conditions and develop a strategy to ensure that land access does not delay the project.
MAXIMA wastewater infrastructure scheme
The MAXIMA programme is designed to meet the wastewater treatment needs of the municipalities of Burlöv, Lomma, Lund and Malmö, as well as receive wastewater from parts of Staffanstorp and Svedala.
The scheme comprises several major infrastructure components:
- A new Sjölunda wastewater treatment plant in Malmö, including new outfall pipelines into the Öresund.
- A new large pumping station at Sjölunda.
- A southern wastewater tunnel beneath Malmö.
- A northern wastewater tunnel connecting Lund to Sjölunda.
- A pressurised wastewater transfer pipeline from Borgeby.
Southern wastewater tunnel: Malmö–Sjölunda
The southern tunnel will run approximately 5.5km from Turbinen in central Malmö to Sjölunda. The main tunnel will have a diameter of 5m and will be connected to two micro-tunnels, each 2m in diameter, with a combined length of 2.4km.
The tunnel will be excavated at depths of approximately 20–35m and is designed to provide a storage capacity of 100,000m³.
Eleven shafts are planned along the alignment. The shaft near Sjölunda will have a diameter of 45m to accommodate the new pumping station, while the remaining shafts will range from 4m to 15m in diameter.
Northern wastewater tunnel: Lund–Sjölunda
The northern tunnel will extend approximately 10km between the Källby treatment plant in Lund and the new Sjölunda facility. It will be constructed at depths of approximately 20–35m, with an internal diameter of 3m and a planned storage capacity of 80,000m³.
Four shafts are planned along the route. The entry shaft will have a diameter of 20m, while the other shafts will range from 9m to 13m.
Procurement and construction schedule
Tunnelling was not scheduled to begin before 2029. The withdrawal of the contract notice means VA SYD must clarify land-access arrangements and review its contracting strategy before proceeding with the tunnel procurement.
MAXIMA has been under consideration since 2017 and represents a major regional investment in wastewater treatment capacity and infrastructure for southern Sweden.