NewsProject Show Case

Breakthrough for DTSS – Phase 2

DTSS Route Map

In order to construct the Deep Tunnel Sewerage System Phase 2, Contract T-09, the 2nd TBM named Yuan Ching with a 7.56m diameter has excavated almost 60m beneath the ground on 15 January 2022. The average performance of this TBM for completing its 2.88 km journey was 28.8 m/day and 347.2 m/month.

Please click here for tunnelingworld archive. Also, visit this webpage and this webpage for more details.

What is your reaction?

Excited
0
Happy
0
In Love
0
Not Sure
0
Silly
0

You may also like

Leave a reply

Your email address will not be published. Required fields are marked *

More in:News