NewsProject Show Case

All Top Brackets have been Installed at the EE2 Emergency Exit in the Tunnel

EE2 Emergency Exit Tunnel Technology

Multiple finishing tasks, including cleaning works, were implemented on the construction site of the tunnel.

On the ramp, on the side of Wolin Island, insulation was made for the bituminous layers. In addition, the structure for the façade was installed, and at the Trafo TK2 station’s construction site, construction works were completed. Moreover, finishing works are still processing, and crucial road infrastructure is being constructed on the roads as well.

All top supports at the EE2 emergency exit have been installed. In the T2 section of the tunnel, an infrastructure installation or energy-intensive barriers were installed. However, in the T1 section, preparations are underway to insulate the road slab. The construction of both emergency exits and prefabricated elements is sealed.

On the island of Uznam’s side, in the starting chamber, the road slab in the western part is boarded and reinforced. Also, concreting of road slabs in the eastern part and preparation for backfilling of the central part of the chassis are underway.

The upper floor was entirely reinforced and concreted. On the intermediate floor, there is a brick escape cage. Finishing works and internal installation works are underway in the Service Center building.

What is your reaction?

Excited
0
Happy
0
In Love
0
Not Sure
0
Silly
0

You may also like

Leave a reply

Your email address will not be published. Required fields are marked *

More in:News