The deadline for the open invitation to tender for the construction work on the state road from the Vuvevica junction on the A1 to the junction on the D8, section km 0 + 613 – km 7 + 480 including the Kozjak tunnel, has been postponed from 23/01/2023 to 31/01/2023.

The 2530 m single-tube tunnel will be for two-way traffic with a safety parallel tunnel. The tunnel is designed for 80 km/h and will be constructed by NATM.

The value of the contract is said to be EUR 83.13 million, excluding VAT. Also, the duration of the contract will be 36 months.

Those interested, contact:
Hrvatske Ceste d.o.o. Zagreb, attn Renata Lukacic, Zagreb
– Tel: +385 14722571
– Fax +385 14722511
– Email: renata.lukacic@hrvatske-ceste.hr

For tender documents click here where tenders must be sent.

Further details are available here.

What is your reaction?

Excited
1
Happy
1
In Love
0
Not Sure
0
Silly
0

You may also like

More in:Features