FeaturesNewsProject Show Case

HS2 has Announced Six Bidders Tender for Civils Work on Next Phase to Crewe

HS2 Phase 2a from West Midlands to Crewe

High Speed 2 Ltd. has revealed six bidders for a key two-part allowing works contract for the next phase of the high-speed rail scheme, extending from the West Midlands to Crewe.

The companies have been nominated for the £240M advanced civil works contract to deliver critical preparatory works along the phase 2a section of HS2 (High Speed 2).

Galliford Try Construction, Bam Construction, John Graham Construction, Laing O’Rourke Construction, Kier Construction, and Skanska Construction are the bidders invited to tender for the contract.

The scope of works is going to comprise environmental mitigation, land assembly, establishment of haul routes and site compounds, and preparing the trace of the line – which will, in turn, allow mobilization and the beginning of major civil works in summer 2024.

The three-year-long contract, splits work along the route into two different packages, with one contractor delivering works for the southern sections and a different contractor delivering the works on the northern sections. Work is planned to start in the autumn of 2022.

HS2 Ltd stated that given the similarity of scope for the south and north contracts, companies should bid for both contracts, yet will not be able to win both packages for capacity and resilience reasons.

The declaration follows HS2 Ltd starting the analysis for the phase 2a DDP (design and delivery partner). It released the pre-qualification questionnaire for the £500M contract in June.

Winner of the DDP package is going to work with HS2 Ltd to lead the delivery of the 58km route, comprising managing and coordinating essential contracts for delivering the railway’s detailed design and construction, which contains 65 bridges, 17 viaducts and track along the route extending from phase one in the Midlands to the southern outskirts of Crewe.

“Extending the phase 2a route to Crewe will support 6,500 construction jobs and deliver new infrastructure that frees up capacity on the West Coast railway and shortens journey times together with an improved passenger experience,” said Ruth Todd, HS2 Ltd chief commercial officer.

    Parts of the advanced civil works comprise:

  • Management, possession, and maintenance of HS2 land containing installation of boundary fencing and security prior to handover to main civil works contractors
  • Establishment of site compounds, access points, plant crossings, diversions and haul roads
  • Installation of some key temporary works crossing current waterway and railway assets to link up a series of haul roads
  • Current utility asset protection and providing temporary connections to works compounds
  • Demolitions along the route and site clearance in advance of the main civils works
  • Ecology and archaeological surveys, planting of new woodland and wildlife translocation to previously prepared new sites

What is your reaction?

Excited
0
Happy
0
In Love
0
Not Sure
0
Silly
0

You may also like

Leave a reply

Your email address will not be published. Required fields are marked *

More in:Features