With attendance of Nepal’s prime minister, Pushpa Kamal Dahal, the final breakthrough on Nepalese Hydro Project, of the 9.5m diameter tunnel took place on the 3.1km section between Face 4 and Face 5 and marked completion of the 8.7km head race tunnel by Patel Engineering Ltd, as this company has reported on LinkedIn.
Also, Arun-3 is SJVN Arun-III Power Development Company’s 900MW run-of-the-river hydropower project on the Arun River in the Sankhuwasabha district of Nepal.
Construction of the 8.7km head race tunnel, a surge shaft, a butterfly valve chamber, two pressure shafts as well as an underground power house complex, are the works of Patel Engineering.