A competitive procedure with negotiation for the Valby tunnel construction to protect Copenhagen and Frederiksberg against flooding in connection with rainfall events is ongoing. The deadline is said to be 30/06/2023.
The tunnel must be able to compile stormwater from Frederiksberg West and Valby and lead it additionally into Kalveboderne through Enghave Kanal close to Sydhavnstippen.
The 2,382 m long tunnel will be excavated about 15 – 21 m below ground level in the limestone. A total of four shafts will be set for the drilling work.
The contract is worth EUR 67.13 million (DKK500 million), excluding VAT. The duration of the contract will be from 20/12/2023 to 30/06/2028.
Those interested can contact HOFOR A/S, attn Jens Vollertzen, Copenhagen:
+45 27954358
– Email: jevo@hofor.dk
And Frederiksberg Spildevand A/S, attn Mikael Koopmann, Frederiksberg:
+45 38185320
– Email: miko@frb-forsyning.dk
For tender documents, where tenders must be sent Click here.
Visit here for further information.