{"id":3702,"date":"2021-06-17T15:57:27","date_gmt":"2021-06-17T15:57:27","guid":{"rendered":"http:\/\/tunnelingworld.com\/?p=3702"},"modified":"2021-06-17T15:57:27","modified_gmt":"2021-06-17T15:57:27","slug":"completing-frogmore-connection-tunnels-secondary-lining","status":"publish","type":"post","link":"https:\/\/tunnelingworld.com\/?p=3702","title":{"rendered":"Completing Frogmore Connection Tunnel&#8217;s secondary lining"},"content":{"rendered":"<p style=\"text-align: justify;\">The connection tunnel between Wandsworth and the main super sewer in West London with 1.1km length, has finished its secondary lining phase and this is a landmark moment for the Tideway project.<\/p>\n<p style=\"text-align: justify;\">The Frogmore Connection Tunnel (FCT) crosses from the northern angle of King George\u2019s Park, through Tideway\u2019s site at Dormay Street, under the Thames and finishes deep beneath the northern bank of the Thames at Carnwath Road in Fulham.<\/p>\n<p style=\"text-align: justify;\">Due to working with expert tunnelling firm Kern, the team used a system of four individual \u2018shutters\u2019 to cast the concrete in situ using a \u2018hit and miss\u2019 sequence the production procedure runs faster. Following a month into the secondary lining production, the UK&#8217;s obligatory lockdown forced the team to halt all work.<\/p>\n<p style=\"text-align: justify;\">Considering the 2.5m internal diameter of the FCT, social distancing was a significant challenge and resuming the production in accordance with the latest guidance needed much efforts, which have done thanks to the Tideway\u2019s main works contractors (Bam Nuttall, Morgan Sindall and Balfour Beatty), along with the efforts of Kern.<\/p>\n<p style=\"text-align: justify;\">As it is illustrated in graphic below, a tunnel boring machine called Charlotte had previously dug the full FCT in two separate drives \u2013 first mining south from Dormay Street to King George\u2019s Park, then (after a short journey by road back to Dormay Street) north to Carnwath Road.<\/p>\n<p style=\"text-align: justify;\"><img loading=\"lazy\" decoding=\"async\" class=\"alignnone size-medium wp-image-3703\" src=\"http:\/\/tunnelingworld.com\/wp-content\/uploads\/2021\/06\/Fig1-1-300x171.png\" alt=\"\" width=\"300\" height=\"171\" \/><\/p>\n<p style=\"text-align: justify;\">Project Director Sally Cox stated: &#8220;Well done to the entire team for completing the secondary lining of the Frogmore Tunnel. It has not been an easy one with the disruption of Covid in the middle of the works, but the team have worked brilliantly in making it a success.&#8221;<\/p>\n<p style=\"text-align: justify;\">While the maximum production rate of this team was 72m, total use of concrete for the secondary lining in this project was 1,420m3 and covered an average of 60m per a week.<\/p>\n<p style=\"text-align: justify;\">Currently scouring both the northern and southern tunnels and completing the contact grouting and fixing any outstanding snagging items, is the next step of this process.<\/p>\n<p style=\"text-align: justify;\">Further information, is accessible <a href=\"https:\/\/www.tideway.london\/news\/site-news\/2021\/june\/secondary-lining-complete-on-frogmore-connection-tunnel\/%23sub-nav\">here<\/a>.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>The connection tunnel between Wandsworth and the main super sewer in West London with 1.1km length, has finished its secondary lining phase and this is a landmark moment for the Tideway project. The Frogmore Connection Tunnel (FCT) crosses from the northern angle of King George\u2019s Park, through Tideway\u2019s site at Dormay Street, under the Thames and finishes deep beneath the northern bank of the Thames at Carnwath Road in Fulham. Due to working with expert tunnelling firm Kern, the team used a system of four individual \u2018shutters\u2019 to cast the concrete in situ using a \u2018hit and miss\u2019 sequence the [&hellip;]<\/p>\n","protected":false},"author":2,"featured_media":3704,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[40],"tags":[491,492,467,187,321,48],"class_list":["post-3702","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-features","tag-frogmore-connection-tunnel","tag-lining","tag-sewer-project","tag-tideway","tag-tunnelling","tag-uk","post--single"],"_links":{"self":[{"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=\/wp\/v2\/posts\/3702","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=3702"}],"version-history":[{"count":0,"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=\/wp\/v2\/posts\/3702\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=\/wp\/v2\/media\/3704"}],"wp:attachment":[{"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=3702"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=3702"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=3702"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}