{"id":20948,"date":"2026-11-18T13:27:30","date_gmt":"2026-11-18T13:27:30","guid":{"rendered":"https:\/\/tunnelingworld.com\/?p=20948"},"modified":"2026-11-18T13:27:30","modified_gmt":"2026-11-18T13:27:30","slug":"chennai-metro-phase-2-corridor-5-tbm-breakthrough","status":"publish","type":"post","link":"https:\/\/tunnelingworld.com\/?p=20948","title":{"rendered":"Chennai Metro completes 1.08km TBM drive on Phase 2 Corridor 5"},"content":{"rendered":"<p>Chennai Metro Rail Limited (CMRL) has achieved a tunnelling milestone on Phase 2 Corridor 5, with tunnel boring machine (TBM) Kurinji completing a 1.08km drive between Kolathur and Srinivasa Nagar metro stations.<\/p>\n<p>The machine broke through at Srinivasa Nagar Station on 13 November 2026, following an excavation period of just over one year.<\/p>\n<h5><strong>Challenging ground conditions and alignment<\/strong><\/h5>\n<p>The tunnel drive involved several engineering and operational challenges, including a tight curve with a radius of approximately 230m and varying geological conditions.<\/p>\n<p>Ground conditions along the alignment ranged from soil and weathered rock to hard rock formations classified between Grades 1 and 5.<\/p>\n<p>TBM Kurinji also had to navigate more than 70 borewells and open wells along the route while tunnelling beneath densely populated residential areas.<\/p>\n<p>With this breakthrough, the cumulative tunnelling completed on Corridor 5 has reached 3.78km.<\/p>\n<h5><strong>Chennai Metro Phase 2 development<\/strong><\/h5>\n<p>Chennai Metro Phase 2 comprises a 118.9km network with three corridors and 128 stations.<\/p>\n<p>Corridor 5 extends approximately 47km from Madhavaram to Sholinganallur. The route includes around 5.8km of underground tunnels, with six of its 48 stations located below ground.<\/p>\n<p>The latest breakthrough represents further progress in the delivery of the corridor&#8217;s underground section.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Chennai Metro Rail Limited (CMRL) has achieved a tunnelling milestone on Phase 2 Corridor 5, with tunnel boring machine (TBM) Kurinji completing a 1.08km drive between Kolathur and Srinivasa Nagar metro stations. The machine broke through at Srinivasa Nagar Station on 13 November 2026, following an excavation period of just over one year. Challenging ground conditions and alignment The tunnel drive involved several engineering and operational challenges, including a tight curve with a radius of approximately 230m and varying geological conditions. Ground conditions along the alignment ranged from soil and weathered rock to hard rock formations classified between Grades 1 [&hellip;]<\/p>\n","protected":false},"author":5,"featured_media":20949,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[4001],"tags":[5335,5625,1423,5992,55,5980,4666],"class_list":["post-20948","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-contract-projects","tag-chennai-metro","tag-chennai-metro-phase-2","tag-cmrl","tag-corridor-5","tag-india","tag-metro-tunnelling","tag-tbm-kurinji","post--single"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v28.8 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Chennai Metro TBM Breakthrough on Phase 2 Corridor 5<\/title>\n<meta name=\"description\" content=\"TBM Kurinji completes a 1.08km drive on Chennai Metro Phase 2 Corridor 5, overcoming a tight curve and challenging ground conditions.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/tunnelingworld.com\/?p=20948\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Chennai Metro TBM Breakthrough on Phase 2 Corridor 5\" \/>\n<meta property=\"og:description\" content=\"TBM Kurinji completes a 1.08km drive on Chennai Metro Phase 2 Corridor 5, overcoming a tight curve and challenging ground conditions.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/tunnelingworld.com\/?p=20948\" \/>\n<meta property=\"og:site_name\" content=\"Tunnelingworld\" \/>\n<meta property=\"article:published_time\" content=\"2026-11-18T13:27:30+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/tunnelingworld.com\/wp-content\/uploads\/2026\/11\/Image-1-10.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"633\" \/>\n\t<meta property=\"og:image:height\" content=\"355\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"rosebell\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"rosebell\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"2 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/?p=20948#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/?p=20948\"},\"author\":{\"name\":\"rosebell\",\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/#\\\/schema\\\/person\\\/4d2f4182b445645aa0b79f3f43560eba\"},\"headline\":\"Chennai Metro completes 1.08km TBM drive on Phase 2 Corridor 5\",\"datePublished\":\"2026-11-18T13:27:30+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/?p=20948\"},\"wordCount\":194,\"image\":{\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/?p=20948#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/tunnelingworld.com\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/Image-1-10.jpg\",\"keywords\":[\"Chennai Metro\",\"Chennai Metro Phase 2\",\"CMRL\",\"Corridor 5\",\"India\",\"metro tunnelling\",\"TBM Kurinji\"],\"articleSection\":[\"Contract\\\/projects\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/?p=20948\",\"url\":\"https:\\\/\\\/tunnelingworld.com\\\/?p=20948\",\"name\":\"Chennai Metro TBM Breakthrough on Phase 2 Corridor 5\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/?p=20948#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/?p=20948#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/tunnelingworld.com\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/Image-1-10.jpg\",\"datePublished\":\"2026-11-18T13:27:30+00:00\",\"author\":{\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/#\\\/schema\\\/person\\\/4d2f4182b445645aa0b79f3f43560eba\"},\"description\":\"TBM Kurinji completes a 1.08km drive on Chennai Metro Phase 2 Corridor 5, overcoming a tight curve and challenging ground conditions.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/?p=20948#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/tunnelingworld.com\\\/?p=20948\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/?p=20948#primaryimage\",\"url\":\"https:\\\/\\\/tunnelingworld.com\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/Image-1-10.jpg\",\"contentUrl\":\"https:\\\/\\\/tunnelingworld.com\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/Image-1-10.jpg\",\"width\":633,\"height\":355,\"caption\":\"Chennai Metro Phase 2 Corridor 5\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/?p=20948#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/tunnelingworld.com\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Chennai Metro completes 1.08km TBM drive on Phase 2 Corridor 5\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/#website\",\"url\":\"https:\\\/\\\/tunnelingworld.com\\\/\",\"name\":\"Tunnelingworld\",\"description\":\"\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/tunnelingworld.com\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/tunnelingworld.com\\\/#\\\/schema\\\/person\\\/4d2f4182b445645aa0b79f3f43560eba\",\"name\":\"rosebell\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/40b92c3f35ab56dec639479a669ce3f5158c2ac3b5cf54852fc3df01779a0812?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/40b92c3f35ab56dec639479a669ce3f5158c2ac3b5cf54852fc3df01779a0812?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/40b92c3f35ab56dec639479a669ce3f5158c2ac3b5cf54852fc3df01779a0812?s=96&d=mm&r=g\",\"caption\":\"rosebell\"},\"url\":\"https:\\\/\\\/tunnelingworld.com\\\/?author=5\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Chennai Metro TBM Breakthrough on Phase 2 Corridor 5","description":"TBM Kurinji completes a 1.08km drive on Chennai Metro Phase 2 Corridor 5, overcoming a tight curve and challenging ground conditions.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/tunnelingworld.com\/?p=20948","og_locale":"en_US","og_type":"article","og_title":"Chennai Metro TBM Breakthrough on Phase 2 Corridor 5","og_description":"TBM Kurinji completes a 1.08km drive on Chennai Metro Phase 2 Corridor 5, overcoming a tight curve and challenging ground conditions.","og_url":"https:\/\/tunnelingworld.com\/?p=20948","og_site_name":"Tunnelingworld","article_published_time":"2026-11-18T13:27:30+00:00","og_image":[{"width":633,"height":355,"url":"https:\/\/tunnelingworld.com\/wp-content\/uploads\/2026\/11\/Image-1-10.jpg","type":"image\/jpeg"}],"author":"rosebell","twitter_card":"summary_large_image","twitter_misc":{"Written by":"rosebell","Est. reading time":"2 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/tunnelingworld.com\/?p=20948#article","isPartOf":{"@id":"https:\/\/tunnelingworld.com\/?p=20948"},"author":{"name":"rosebell","@id":"https:\/\/tunnelingworld.com\/#\/schema\/person\/4d2f4182b445645aa0b79f3f43560eba"},"headline":"Chennai Metro completes 1.08km TBM drive on Phase 2 Corridor 5","datePublished":"2026-11-18T13:27:30+00:00","mainEntityOfPage":{"@id":"https:\/\/tunnelingworld.com\/?p=20948"},"wordCount":194,"image":{"@id":"https:\/\/tunnelingworld.com\/?p=20948#primaryimage"},"thumbnailUrl":"https:\/\/tunnelingworld.com\/wp-content\/uploads\/2026\/11\/Image-1-10.jpg","keywords":["Chennai Metro","Chennai Metro Phase 2","CMRL","Corridor 5","India","metro tunnelling","TBM Kurinji"],"articleSection":["Contract\/projects"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/tunnelingworld.com\/?p=20948","url":"https:\/\/tunnelingworld.com\/?p=20948","name":"Chennai Metro TBM Breakthrough on Phase 2 Corridor 5","isPartOf":{"@id":"https:\/\/tunnelingworld.com\/#website"},"primaryImageOfPage":{"@id":"https:\/\/tunnelingworld.com\/?p=20948#primaryimage"},"image":{"@id":"https:\/\/tunnelingworld.com\/?p=20948#primaryimage"},"thumbnailUrl":"https:\/\/tunnelingworld.com\/wp-content\/uploads\/2026\/11\/Image-1-10.jpg","datePublished":"2026-11-18T13:27:30+00:00","author":{"@id":"https:\/\/tunnelingworld.com\/#\/schema\/person\/4d2f4182b445645aa0b79f3f43560eba"},"description":"TBM Kurinji completes a 1.08km drive on Chennai Metro Phase 2 Corridor 5, overcoming a tight curve and challenging ground conditions.","breadcrumb":{"@id":"https:\/\/tunnelingworld.com\/?p=20948#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/tunnelingworld.com\/?p=20948"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/tunnelingworld.com\/?p=20948#primaryimage","url":"https:\/\/tunnelingworld.com\/wp-content\/uploads\/2026\/11\/Image-1-10.jpg","contentUrl":"https:\/\/tunnelingworld.com\/wp-content\/uploads\/2026\/11\/Image-1-10.jpg","width":633,"height":355,"caption":"Chennai Metro Phase 2 Corridor 5"},{"@type":"BreadcrumbList","@id":"https:\/\/tunnelingworld.com\/?p=20948#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/tunnelingworld.com\/"},{"@type":"ListItem","position":2,"name":"Chennai Metro completes 1.08km TBM drive on Phase 2 Corridor 5"}]},{"@type":"WebSite","@id":"https:\/\/tunnelingworld.com\/#website","url":"https:\/\/tunnelingworld.com\/","name":"Tunnelingworld","description":"","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/tunnelingworld.com\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Person","@id":"https:\/\/tunnelingworld.com\/#\/schema\/person\/4d2f4182b445645aa0b79f3f43560eba","name":"rosebell","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/secure.gravatar.com\/avatar\/40b92c3f35ab56dec639479a669ce3f5158c2ac3b5cf54852fc3df01779a0812?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/40b92c3f35ab56dec639479a669ce3f5158c2ac3b5cf54852fc3df01779a0812?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/40b92c3f35ab56dec639479a669ce3f5158c2ac3b5cf54852fc3df01779a0812?s=96&d=mm&r=g","caption":"rosebell"},"url":"https:\/\/tunnelingworld.com\/?author=5"}]}},"_links":{"self":[{"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=\/wp\/v2\/posts\/20948","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=\/wp\/v2\/users\/5"}],"replies":[{"embeddable":true,"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=20948"}],"version-history":[{"count":1,"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=\/wp\/v2\/posts\/20948\/revisions"}],"predecessor-version":[{"id":20950,"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=\/wp\/v2\/posts\/20948\/revisions\/20950"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=\/wp\/v2\/media\/20949"}],"wp:attachment":[{"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=20948"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=20948"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/tunnelingworld.com\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=20948"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}